NOTICE
OF ACCELERATION (CONSTRUCTIVE)
Date
Mr. Contracting Officer
(Address)
Re: Acceleration of Work
Contract No.
Dear Sir:
By previous letter to you of (date), I
request a time extension for (reason). Since you have refused to grant me a
time extension for those excusable delays, I cannot complete the work by the
current contract completion date without accelerating. I therefore consider you
refusal to issue a time extension to be a direction to accelerate the work, and
therefore, a change to the contract.
I will be forwarding my Request for Equitable Adjustment for this change when the extra costs can be compiled.