NOTICE
OF IMPROPER WITHHOLDING
OF
PROGRESS PAYMENTS - DAMAGES
Date
Mr. Contracting Officer
(Address)
Re: Progress Payment No.
Contract No.
Dear Sir:
I am requesting immediate payment of the
monies withheld on the referenced progress payment, in the amount of $ .
This money has been improperly withheld and is causing me damages.
I am a small business contractor without
unlimited resources. Without my earned progress payment, I cannot fully pay my
sub-contractors and suppliers, nor am I able to continue with the work. I
consider this improper action of the Government to be an abuse of discretion
and a material breach of contract.
I would like a meeting with the Contracting
Officer as soon as possible to discuss this matter.