SCHEDULE
–
RESPONSE
TO GOVERNMENT DISAPPROVAL
OF
EARLY COMPLETION
Date
Mr. Contracting Officer
(Address)
Re: Construction Schedule
Contract No.
Dear Sir:
By letter (transmittal) dated , you
disapproved our schedule because it shows that we plan to complete the work in
advance of the contract completion date.
The contract specified that we are
responsible for scheduling the work, and we have the right to schedule the work
in the most efficient manner. Surely the Government does not object to having
the benefit of the completed facilities sooner than it had planned.
We believe that we can complete the work
early, and that is the manner in which we are going to prosecute this job. We
do not plan to change our work schedule. As directed, we are submitting a new
schedule showing completion of the work on the contract completion date.
However, we will proceed with the work in accordance with our early completion
schedule.
If you want to take over the scheduling for
this project, please send us the Government’s schedule and direction to proceed
with that schedule, along with a change order that we can price for
implementing your schedule