SCHEDULE –

RESPONSE TO GOVERNMENT DISAPPROVAL

 

Date

 

Mr. Contracting Officer

 (Address)

Re: Construction Schedule

Contract No.

Dear Sir:

By letter (transmittal) dated , you disapproved our schedule. We have reviewed your comment, and they are not valid with regard to our method of accomplishing the work.

 Specifically, (describe problems here)

 

  

The contract specified that we are responsible for scheduling the work, and we have the right to schedule the work in the most efficient manner. We therefore do not plan to change our schedule.

 

If you want to take over the scheduling for this project, please send us the Government’s schedule and direction to proceed with that schedule, along with a change order that we can price for implementing your schedule